Procurement

Request for Proposal (RFP)

The solicitation used in negotiated acquisitions to describe what the buyer needs and ask for proposals that will be judged on stated evaluation factors, not on price alone.

In context

How Request for Proposal works in supplier diversity

FAR 15.203 says requests for proposals communicate the government's requirement and solicit proposals in negotiated acquisitions. At a minimum an RFP for a competitive acquisition must describe the requirement, the anticipated terms and conditions, the information each proposal must contain, and the evaluation factors and significant subfactors with their relative importance. Past performance is a common factor, and FAR 15.305 requires the RFP to say how firms with no relevant record will be treated.

Timing is set by FAR Part 5. For a non-commercial action expected to exceed the simplified acquisition threshold ($350,000), the agency must allow at least 30 days to respond after the solicitation is issued (FAR 5.203). Deadlines are strict: under FAR 15.208, a proposal received after the exact time set for receipt is late and is considered only in narrow cases, for example an electronic submission that reached the government's initial point of entry by 5:00 p.m. one working day before the due date.

The overhaul encourages more contact before the RFP. RFO 15.101 encourages draft RFPs, industry conferences and requests for information, and states that RFI responses are not offers. For commercial buys above $9 million, RFO 12.201-2 calls the RFP the preferred method over sealed bidding because it allows past performance to be evaluated.

For your business

What it means for your certification

Read the RFP's set-aside designation and NAICS code first: they decide whether you can bid as a prime and under which size standard. If you are other than small and the contract is expected to exceed $900,000 ($2 million for construction), expect to submit a small business subcontracting plan, which is where certified subcontractors get named. Small firms without a federal track record should use the past performance section's allowances for commercial, state and local work and for joint venture or first-tier subcontract experience.

Example

An example scenario

Sources

Where this definition comes from

Checked against these sources on . Spot an error? See our corrections log.

The certification quiz checks your business against every certification we track. The result is a ranked list with the buyers each one opens. Or open the certification reference for the full guides.